Ascension St. Michael’s Hospital – Breast Center
Stevens Point, WI
Delivery Method: General Contractor
Architect: Hammel, Green and Abrahamson
Ascension Saint Michael’s Hospital – Breast Center was a renovation and remodel of clinical space totalling a little over 9,000 square feet. Construction started in January of 2018 and finished in August of 2018.
The Breast Center was such a unique project as it set out to create an all-encompassing healing center for breast care in Central Wisconsin. This project was widely supported by the community with several million dollars of contributions being pledged.
Schedules were very important as this was an important project for the community. Ellis worked hard to get the project done in a timely manner and exceeded expectations by completing four weeks sooner than expected.
One top safety priority was dust control and infection control for all patients and staff that were in the proximity of the construction area both internally and externally.